Construction of 1No. 2 Unit Classroom Block at Kakusuazo

Construction of 1No. 2 Unit Classroom Block

Project Summary

Sector

Education

Location

Kakusuazo

Stage

Construction of 1No. 2 Unit Classroom Block

Contracting Entity

Nzema East Municipal Assembly

Publication Date: Tue Mar 23 2021
Estimated Value: GH¢ 175,278.82 US$ 30,220.49

Project Identification

Project Reference Number:
WR/NEMA/WKS/DDF/RFG/O4/2021
Project Name:
Construction Of 1no. 2 Unit Classroom Block At Kakusuazo
Sector:
Education
Sub sector:
Education
Project Location:
Kakusuazo
Purpose:
To enhance inclusive and equitable access to, and participation in quality education at all levels
Project Description:
Construction of 1No. 2 Unit Classroom Block

Project Preparation

Project Scope:

Construction Of 1no. 2 Unit Classroom Block

Environmental Impact:

No Impact Of Environmental Changes

Land and Settlement Impact:

Increase In School Enrollment

Expected Life of Asset:

40 years

Contact Details:

Funding Source:

Dacf - Responsiveness Factor Grant

Project Budget:
GH¢ 175,278.82
Project Budget Approval Date:
Tue Mar 23 2021

Tender Management

Initiation


Procuring Entity:

Nzema East Municipal Assembly

Procuring Entity Contact Details:

0241365880
nema@yupmail.com
NEMA STREET

Procurement Process:

Competitive (National Competitive Tendering)

Procurement Method:

Open

Bidder(s):
# Bidder(s) Country
No data found
No data found

Award


Number of Firms Tendering:

3

Cost Estimate:

GH¢ 175,278.52

Contracting


Contract Administrative Entity:

Nzema East Municipal Assembly

Contract Type:

Admeasurement

Contract Title:

Construction Of 1no. 2 Unit Classroom Block At Kakusuazo

Contract Firm(s):
# Name of Firm Description
No data found
No data found
Contract Price:

GH¢ 175,278.52

Contract Scope of Work:

Construction of 1no. 2 Unit Classroom Block

Contract Start Date:

Fri Apr 09 2021

Contract Duration:

From: Fri Apr 09 2021
To:
In Days: NaN

Consultant:
# Consultant Description of Role
No data found
No data found
Contract Status:
# Contract Status Reason Date
1 Open Recently commenced Wed Nov 15 2023 11:33:39 GMT+0000 (Coordinated Universal Time)
#1 Open
Contract Status
Open
Reason
Recently commenced
Date
Wed Nov 15 2023 11:33:39 GMT+0000 (Coordinated Universal Time)

Contract Implementation

Variation to Contract Price:

Escalation of Contract Price:

Variation to Contract Scope:

Reasons for Price Changes:

Reasons for Scope Changes:

Reasons for Duration Changes:

Project Completion

Project Status:
# Project Status Reason Date
No data found
No data found
Completion Cost:

GH¢ 175,278.82

Completion Date:

Scope at Completion:

Construction of 1No. 2 Unit Classroom Block

Reasons for Project Changes:
# Reason Recorded Date
No data found
No data found
Reference to Audit and Evaluation Reports:
# Reference to Evaluation Report Recorded Date
No data found
No data found

Milestone

There are no milestones

Project Images