Construction Of 1no. 32 Bay Partitioned Market Shed ( Mpintsin Market)

Construction of 1no. 32 Bay Partitioned Market Shed and External Works at Mpintsin

Project Summary

Sector

Economy

Location

Mpintsin

Stage

Construction of 1no. 32 Bay Partitioned Market Shed

Contracting Entity

Stma - Sekondi-Takoradi Municipal Assembly

Publication Date: Thu Jun 09 2022
Estimated Value: GH¢ 192,861.54 US$ 40,774.11

Project Identification

Project Reference Number:
WR/STMA/WKS/NCT/02/2018
Project Name:
Construction Of 1no. 32 Bay Partitioned Market Shed ( Mpintsin Market)
Sector:
Economy
Sub sector:
Economic
Project Location:
Mpintsin
Purpose:
Market facility for economic activity
Project Description:
Construction of 1no. 32 Bay Partitioned Market Shed

Project Preparation

Project Scope:

Construction Of 1no. 32 Bay Partitioned Market Shed And External Works At Mpintsin

Environmental Impact:

The Project Will Serve As A Market Facility Which Will Enhance Buying And Selling Activity In The Market.

Land and Settlement Impact:

The Project Will Enhance Marketing Activities

Expected Life of Asset:

25 years

Contact Details:

Funding Source:

Dacf - Responsiveness Factor Grant

Project Budget:
GH¢ 192,861.54
Project Budget Approval Date:
Thu Jun 09 2022

Tender Management

Initiation


Procuring Entity:

Sekondi-Takoradi Metropolitan Assembly

Procuring Entity Contact Details:

0312046371
info@stma.gov.gh
STMA Road

Procurement Process:

Competitive (National Competitive Tendering)

Procurement Method:

Open

Bidder(s):
# Bidder(s) Country
1 Noble Kingdom Royals Company Limited Ghana
2 Us Construction Limited Ghana
3 Standard Construction & Eng. Company Limited Ghana
#1 Noble Kingdom Royals Company Limited
Bidder
Noble Kingdom Royals Company Limited
Country
Ghana
#2 Us Construction Limited
Bidder
Us Construction Limited
Country
Ghana
#3 Standard Construction & Eng. Company Limited
Bidder
Standard Construction & Eng. Company Limited
Country
Ghana

Award


Number of Firms Tendering:

3

Cost Estimate:

GH¢ 192,861.54

Contracting


Contract Administrative Entity:

Stma - Sekondi-Takoradi Municipal Assembly

Contract Type:

Admeasurement

Contract Title:

Construction Of 1no. 32 Bay Partitioned Market Shed And External Works At Mpintsin

Contract Firm(s):
# Name of Firm Description
1 Standard Construction & Eng. Company Limited N/A
#1 Standard Construction & Eng. Company Limited
Name of Firm
Standard Construction & Eng. Company Limited
Description
N/A
Contract Price:

GH¢ 192,861.54

Contract Scope of Work:

Construction of 1no. 32 Bay Partitioned Market Shed and External Works

Contract Start Date:

Thu Aug 02 2018

Contract Duration:

From: Thu Aug 02 2018
To: Fri Nov 29 2019
In Days: 484

Consultant:
# Consultant Description of Role
1 Stma Works Department N/A
#1 Stma Works Department
Consultant
Stma Works Department
Description of Role
N/A
Contract Status:
# Contract Status Reason Date
1 Closed N/A Wed Jun 29 2022 11:02:59 GMT+0000 (Coordinated Universal Time)
#1 Closed
Contract Status
Closed
Reason
N/A
Date
Wed Jun 29 2022 11:02:59 GMT+0000 (Coordinated Universal Time)

Contract Implementation

Variation to Contract Price:

GH¢ 0.00

Escalation of Contract Price:

GH¢ 0.00

Variation to Contract Scope:

No

Reasons for Price Changes:

N/A

Reasons for Scope Changes:

N/A

Reasons for Duration Changes:

N/A

Project Completion

Project Status:
# Project Status Reason Date
1 Completed N/A Wed Jun 29 2022 10:59:43 GMT+0000 (Coordinated Universal Time)
#1 Completed
Project Status
Completed
Reason
N/A
Date
Wed Jun 29 2022 10:59:43 GMT+0000 (Coordinated Universal Time)
Completion Cost:

GH¢ 192,785.00

Completion Date:

Fri Nov 29 2019

Scope at Completion:

Construction of 1no. 32 Bay Partitioned Market Shed and External Works

Reasons for Project Changes:
# Reason Recorded Date
1 There Was No Change On The Project Fri Jul 15 2022
#1 Fri Jul 15 2022
Reason
There Was No Change On The Project
Recorded Date
Fri Jul 15 2022
Reference to Audit and Evaluation Reports:
# Reference to Evaluation Report Recorded Date
1 There Was No Adverse Issue After Audit Was Conducted On The Project. Thu May 07 2020
#1 Thu May 07 2020
Reference to Evaluation Report
There Was No Adverse Issue After Audit Was Conducted On The Project.
Recorded Date
Thu May 07 2020

Milestone

There are no milestones