Construction Of 1no. 32 Bay Partitioned Market Shed

Construction of 1no. 32 Bay Partitioned Market Shed and External Works at Diabenekrom

Project Summary

Sector

Economy

Location

Diabenekrom

Stage

Construction of 1no. 32 Bay Partitioned Market Shed

Contracting Entity

Stma - Sekondi-Takoradi Municipal Assembly

Publication Date: Wed Jun 08 2022
Estimated Value: GH¢ 199,042.30 US$ 41,815.61

Project Identification

Project Reference Number:
WR/STMA/WKS/NCT/01/2018
Project Name:
Construction Of 1no. 32 Bay Partitioned Market Shed
Sector:
Economy
Sub sector:
Economic
Project Location:
Diabenekrom
Purpose:
The project will serve as a market facility which will enhance buying and selling activity in the market.
Project Description:
Construction of 1no. 32 Bay Partitioned Market Shed

Project Preparation

Project Scope:

Construction Of 1no. 32 Bay Partitioned Market Shed And External Works At Diabenekrom

Environmental Impact:

N/A

Land and Settlement Impact:

The Project Will Enhance Marketing Activities

Expected Life of Asset:

25 years

Contact Details:

Funding Source:

Dacf - Responsiveness Factor Grant

Project Budget:
GH¢ 199,042.30
Project Budget Approval Date:
Wed Jun 08 2022

Tender Management

Initiation


Procuring Entity:

Sekondi-Takoradi Metropolitan Assembly

Procuring Entity Contact Details:

0312046371
info@stma.gov.gh
STMA Road

Procurement Process:

Competitive (National Competitive Tendering)

Procurement Method:

Open

Bidder(s):
# Bidder(s) Country
1 Akyere And Associates Limited Ghana
2 Soloclem Company Limited Ghana
3 M/S Emnesday Company Ltd Ghana
4 Transactors Limited Ghana
#1 Akyere And Associates Limited
Bidder
Akyere And Associates Limited
Country
Ghana
#2 Soloclem Company Limited
Bidder
Soloclem Company Limited
Country
Ghana
#3 M/S Emnesday Company Ltd
Bidder
M/S Emnesday Company Ltd
Country
Ghana
#4 Transactors Limited
Bidder
Transactors Limited
Country
Ghana

Award


Number of Firms Tendering:

4

Cost Estimate:

GH¢ 199,042.30

Contracting


Contract Administrative Entity:

Stma - Sekondi-Takoradi Municipal Assembly

Contract Type:

Admeasurement

Contract Title:

Construction Of 1no. 32 Bay Partitioned Market Shed And External Works At Diabenekrom

Contract Firm(s):
# Name of Firm Description
1 Soloclem Company Limited N/A
#1 Soloclem Company Limited
Name of Firm
Soloclem Company Limited
Description
N/A
Contract Price:

GH¢ 199,042.30

Contract Scope of Work:

Construction of 1no. 32 Bay Partitioned Market Shed and External Works

Contract Start Date:

Thu Aug 02 2018

Contract Duration:

From: Thu Aug 02 2018
To: Fri Nov 29 2019
In Days: 484

Consultant:
# Consultant Description of Role
1 Stma Works Department N/A
#1 Stma Works Department
Consultant
Stma Works Department
Description of Role
N/A
Contract Status:
# Contract Status Reason Date
1 Closed Recently commenced Tue Jun 07 2022 16:25:33 GMT+0000 (Coordinated Universal Time)
#1 Closed
Contract Status
Closed
Reason
Recently commenced
Date
Tue Jun 07 2022 16:25:33 GMT+0000 (Coordinated Universal Time)

Contract Implementation

Variation to Contract Price:

GH¢ 0.00

Escalation of Contract Price:

GH¢ 0.00

Variation to Contract Scope:

No

Reasons for Price Changes:

N/A

Reasons for Scope Changes:

N/A

Reasons for Duration Changes:

N/A

Project Completion

Project Status:
# Project Status Reason Date
1 Completed N/A Wed Jun 29 2022 08:48:17 GMT+0000 (Coordinated Universal Time)
#1 Completed
Project Status
Completed
Reason
N/A
Date
Wed Jun 29 2022 08:48:17 GMT+0000 (Coordinated Universal Time)
Completion Cost:

GH¢ 218,826.90

Completion Date:

Fri Nov 29 2019

Scope at Completion:

Construction of 1no. 32 Bay Partitioned Market Shed and External Works

Reasons for Project Changes:
# Reason Recorded Date
1 There Was No Change On The Project Fri Jul 15 2022
#1 Fri Jul 15 2022
Reason
There Was No Change On The Project
Recorded Date
Fri Jul 15 2022
Reference to Audit and Evaluation Reports:
# Reference to Evaluation Report Recorded Date
1 There Was No Adverse Issue After Audit Was Conducted Thu May 07 2020
#1 Thu May 07 2020
Reference to Evaluation Report
There Was No Adverse Issue After Audit Was Conducted
Recorded Date
Thu May 07 2020

Milestone

There are no milestones

Project Images

Construction Of 1no. 32 Bay Partitioned Market Shed

Image 1

Construction Of 1no. 32 Bay Partitioned Market Shed

Image 2

Construction Of 1no. 32 Bay Partitioned Market Shed

Image 3

Construction Of 1no. 32 Bay Partitioned Market Shed

Image 4