Construction Of 1no. 6-Unit Classroom Block

6-Unit Classroom Block, Office, Store, Computer Room, 1No. 6-Seater Enviro-Loo Toilet Facility, 2-Bay Urinal and Landscaping

Project Summary

Sector

Education

Location

Domeabra

Stage

6-Unit Classroom Block, Office, Store, Computer Room, 1No. 6-Seater Enviro-Loo Toilet Facility, 2-Bay Urinal and Landscaping

Contracting Entity

Tarkwa Nsuaem Municipal Assembly

Publication Date: Thu Oct 25 2018
Estimated Value: GH¢ 500,000.00 US$ 96,153.80

Project Identification

Project Reference Number:
WR/TNMA//WKS/NCT/08/2019
Project Name:
Construction Of 1no. 6-Unit Classroom Block
Sector:
Education
Sub sector:
Education
Project Location:
Domeabra
Purpose:
Increased enrolment and access to basic Education. Improved condition for teaching and learning
Project Description:
6-Unit Classroom Block, Office, Store, Computer Room, 1No. 6-Seater Enviro-Loo Toilet Facility, 2-Bay Urinal and Landscaping

Project Preparation

Project Scope:

6-Unit Classroom Block, Office, Store, Computer Room, 1no. 6-Seater Enviro-Loo Toilet Facility, 2-Bay Urinal And Landscaping

Environmental Impact:

Re-Afforestation.

Land and Settlement Impact:

Yes

Expected Life of Asset:

25yrs years

Contact Details:

Funding Source:

Minerals Development Fund

Project Budget:
GH¢ 500,000.00
Project Budget Approval Date:
Thu Oct 25 2018

Tender Management

Initiation


Procuring Entity:

Tarkwa Nsuaem Municipal Assembly

Procuring Entity Contact Details:

0507128000
tarkwansuaem@gmail.com
Tarkwa- Ahwetieso road

Procurement Process:

Competitive (National Competitive Tendering)

Procurement Method:

Open

Bidder(s):
# Bidder(s) Country
1 M/S Us Global Co. Limited Ghana
2 M/S Joerica Company Limited Ghana
3 M/S Wilcornah Enterprise Ghana
#1 M/S Us Global Co. Limited
Bidder
M/S Us Global Co. Limited
Country
Ghana
#2 M/S Joerica Company Limited
Bidder
M/S Joerica Company Limited
Country
Ghana
#3 M/S Wilcornah Enterprise
Bidder
M/S Wilcornah Enterprise
Country
Ghana

Award


Number of Firms Tendering:

3

Cost Estimate:

GH¢ 500,000.00

Contracting


Contract Administrative Entity:

Tarkwa Nsuaem Municipal Assembly

Contract Type:

Lump Sum

Contract Title:

Construction Of 6-Unit Classroom Block, Office, Store, Computer Room, 1no. 6-Seater Enviro-Loo Toilet Facility, 2-Bay Urinal And Landscaping

Contract Firm(s):
# Name of Firm Description
1 M/S Us Construction Limited
#1 M/S Us Construction Limited
Name of Firm
M/S Us Construction Limited
Description
Contract Price:

GH¢ 548,696.45

Contract Scope of Work:

1 No. 6-Unit Classroom Block, Office, Store, Computer Room, 1No. 6-Seater Enviro-Loo Toilet Facility, 2-Bay Urinal and Landscaping

Contract Start Date:

Fri Aug 23 2019

Contract Duration:

From: Fri Aug 23 2019
To: Fri Sep 17 2021
In Days: 756

Consultant:
# Consultant Description of Role
1 Tnma Works Department
#1 Tnma Works Department
Consultant
Tnma Works Department
Description of Role
Contract Status:
# Contract Status Reason Date
1 Closed Project is Complete and handed over Mon Jun 27 2022 15:56:14 GMT+0000 (Coordinated Universal Time)
#1 Closed
Contract Status
Closed
Reason
Project is Complete and handed over
Date
Mon Jun 27 2022 15:56:14 GMT+0000 (Coordinated Universal Time)

Contract Implementation

Variation to Contract Price:

GH¢ 0.00

Escalation of Contract Price:

GH¢ 0.00

Variation to Contract Scope:

N/A

Reasons for Price Changes:

n/a

Reasons for Scope Changes:

n/a

Reasons for Duration Changes:

The Outbreak of Covid-19 Pandemic

Project Completion

Project Status:
# Project Status Reason Date
1 Completed Project is completed and handed over Tue Jun 28 2022 15:07:01 GMT+0000 (Coordinated Universal Time)
#1 Completed
Project Status
Completed
Reason
Project is completed and handed over
Date
Tue Jun 28 2022 15:07:01 GMT+0000 (Coordinated Universal Time)
Completion Cost:

GH¢ 548,696.50

Completion Date:

Fri Sep 17 2021

Scope at Completion:

Completed

Reasons for Project Changes:
# Reason Recorded Date
1 No Project Changes Thu Sep 30 2021
#1 Thu Sep 30 2021
Reason
No Project Changes
Recorded Date
Thu Sep 30 2021
Reference to Audit and Evaluation Reports:
# Reference to Evaluation Report Recorded Date
1 No Audit Issues Wed Dec 15 2021
#1 Wed Dec 15 2021
Reference to Evaluation Report
No Audit Issues
Recorded Date
Wed Dec 15 2021

Milestone

There are no milestones

Project Images

Construction Of 1no. 6-Unit Classroom Block

Image 1

Construction Of 1no. 6-Unit Classroom Block

Image 2

Construction Of 1no. 6-Unit Classroom Block

Image 3

Construction Of 1no. 6-Unit Classroom Block

Image 4

Construction Of 1no. 6-Unit Classroom Block

Image 5