Construction of 1No. 2 Unit Classroom Block at Allah-Essuna Primary School

Clearing of site, excavation and earth works, hardcore filling, concrete works, blockwork, roofing, carpentry works, joinery, metal works, electrical works, plumbing works, finishing, painting and decorating, external works

Project Summary

Sector

Education

Location

Axim

Stage

Construction of 1No. 2 Unit Classroom Block at Alh-Essuna Primary School

Contracting Entity

Nzema East Municipal Assembly

Publication Date: Tue Jul 16 2019
Estimated Value: GH¢ 135,014.34 US$ 25,964.30

Project Identification

Project Reference Number:
WR/NEMA/WKS/DDF/01/19
Project Name:
Construction Of 1no. 2 Unit Classroom Block At Allah-Essuna Primary School
Sector:
Education
Sub sector:
Education
Project Location:
Axim
Purpose:
The objective of the project was to get a suitable classroom block to accommodate the Kindergarten pupils of Allah-Essuna Primary School
Project Description:
Construction of 1No. 2 Unit Classroom Block at Alh-Essuna Primary School

Project Preparation

Project Scope:

Clearing Of Site, Excavation And Earth Works, Hardcore Filling, Concrete Works, Blockwork, Roofing, Carpentry Works, Joinery, Metal Works, Electrical Works, Plumbing Works, Finishing, Painting And Decorating, External Works

Environmental Impact:

Reafforestation

Land and Settlement Impact:

Increase In School Enrollment

Expected Life of Asset:

25 years

Contact Details:

Funding Source:

Dacf - Responsiveness Factor Grant

Project Budget:
GH¢ 135,014.34
Project Budget Approval Date:
Tue Jul 16 2019

Tender Management

Initiation


Procuring Entity:

Nzema East Municipal Assembly

Procuring Entity Contact Details:

0241365880
nema@yupmail.com
NEMA STREET

Procurement Process:

National Competitive Tendering

Procurement Method:

Open

Bidder(s):
# Bidder(s) Country
1 Joerica Company Limited Ghana
2 Us Global Company Limited Ghana
#1 Joerica Company Limited
Bidder
Joerica Company Limited
Country
Ghana
#2 Us Global Company Limited
Bidder
Us Global Company Limited
Country
Ghana

Award


Number of Firms Tendering:

4

Cost Estimate:

GH¢ 150,000.00

Contracting


Contract Administrative Entity:

Nzema East Municipal Assembly

Contract Type:

Construction

Contract Title:

Construction Of 1no. 2 Unit Kg Block At Allah-Essuna Primary School

Contract Firm(s):
# Name of Firm Description
1 M/S. Joerica Co. Ltd
#1 M/S. Joerica Co. Ltd
Name of Firm
M/S. Joerica Co. Ltd
Description
Contract Price:

GH¢ 135,014.34

Contract Scope of Work:

Clearing of site, excavation and earth works, hardcore filling, concrete works, blockwork, roofing, carpentry works, joinery, metal works, electrical works, plumbing works, finishing, painting and decorating, external works

Contract Start Date:

Mon Jul 22 2019

Contract Duration:

From: Mon Jul 22 2019
To: Thu Jul 16 2020
In Days: 360

Consultant:
# Consultant Description of Role
1 Eric Yeboah Municipal Works Engineer
#1 Eric Yeboah
Consultant
Eric Yeboah
Description of Role
Municipal Works Engineer
Contract Status:
# Contract Status Reason Date
1 Active Project is completed and fully in use Tue May 24 2022 11:04:59 GMT+0000 (Coordinated Universal Time)
#1 Active
Contract Status
Active
Reason
Project is completed and fully in use
Date
Tue May 24 2022 11:04:59 GMT+0000 (Coordinated Universal Time)

Contract Implementation

Variation to Contract Price:

GH¢ 0.00

Escalation of Contract Price:

GH¢ 0.00

Variation to Contract Scope:

N/A

Reasons for Price Changes:

N/A

Reasons for Scope Changes:

No Scope Changes

Reasons for Duration Changes:

N/A

Project Completion

Project Status:
# Project Status Reason Date
1 Completed Project completed and in use Tue Jun 28 2022 13:47:38 GMT+0000 (Coordinated Universal Time)
#1 Completed
Project Status
Completed
Reason
Project completed and in use
Date
Tue Jun 28 2022 13:47:38 GMT+0000 (Coordinated Universal Time)
Completion Cost:

GH¢ 135,014.34

Completion Date:

Thu Jan 16 2020

Scope at Completion:

Clearing of site, excavation and earth works, hardcore filling, concrete works, blockwork, roofing, carpentry works, joinery, metal works, electrical works, plumbing works, finishing, painting and decorating, external works

Reasons for Project Changes:
# Reason Recorded Date
1 No Change Thu Jul 16 2020
#1 Thu Jul 16 2020
Reason
No Change
Recorded Date
Thu Jul 16 2020
Reference to Audit and Evaluation Reports:
# Reference to Evaluation Report Recorded Date
No data found
No data found

Milestone

There are no milestones

Project Images

Construction of 1No. 2 Unit Classroom Block at Allah-Essuna Primary School

Image 1