Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

1 no.2 unit KG Block with Office, Kitchen and Urinal/ Toilet Facilities and Furniture

Project Summary

Sector

Education

Location

Anto-Aboso

Stage

Construction of 1 no.2 unit KG Block with Office, Kitchen and Urinal/ Toilet Facilities and Furniture

Contracting Entity

Shama District Assembly

Publication Date: Tue Aug 22 2023
Estimated Value: GH¢ 473,800.00 US$ 41,375.00

Project Identification

Project Reference Number:
WR/SDA/WKS/008/22
Project Name:
Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School
Sector:
Education
Sub sector:
Education
Project Location:
Anto-Aboso
Purpose:
To improve access to quality education.
Project Description:
Construction of 1 no.2 unit KG Block with Office, Kitchen and Urinal/ Toilet Facilities and Furniture

Project Preparation

Project Scope:

1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture

Environmental Impact:

Epa Certificate And Has Been Acquired And The Report Is Available

Land and Settlement Impact:

Epa Certificate And Has Been Acquired And The Report Is Available

Expected Life of Asset:

50 Years and it will be maintained as and when the need arises. years

Contact Details:

Funding Source:

District Assemblies Common Fund

Project Budget:
GH¢ 473,800.00
Project Budget Approval Date:
Tue Aug 22 2023

Tender Management

Initiation


Procuring Entity:

Shama District Assembly

Procuring Entity Contact Details:

0246153277
info@shamadistrict.gov.gh
P. O. Box 37, Shama

Procurement Process:

Competitive (National Competitive Tendering)

Procurement Method:

Open

Bidder(s):
# Bidder(s) Country
1 Ashcab Co. Ltd Ghana
2 I. B Clements Co. Ltd Ghana
3 Powerful Ventures Limited Ghana
#1 Ashcab Co. Ltd
Bidder
Ashcab Co. Ltd
Country
Ghana
#2 I. B Clements Co. Ltd
Bidder
I. B Clements Co. Ltd
Country
Ghana
#3 Powerful Ventures Limited
Bidder
Powerful Ventures Limited
Country
Ghana

Award


Number of Firms Tendering:

4

Cost Estimate:

GH¢ 473,800.00

Contracting


Contract Administrative Entity:

Shama District Assembly

Contract Type:

Lump Sum

Contract Title:

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

Contract Firm(s):
# Name of Firm Description
1 Powerful Ventures Ltd
#1 Powerful Ventures Ltd
Name of Firm
Powerful Ventures Ltd
Description
Contract Price:

GH¢ 473,800.00

Contract Scope of Work:

Excavation, Hardcore filling, cutting/ clearing, Concrete works, Reinforcement work, Formwork, Block work, Roofing, Woodwork, ironmongery work, metal work, Plumbing

Contract Start Date:

Thu Sep 15 2022

Contract Duration:

From: Thu Sep 15 2022
To: Tue Mar 14 2023
In Days: 180

Consultant:
# Consultant Description of Role
No data found
No data found
Contract Status:
# Contract Status Reason Date
1 Open Recently commenced Fri May 24 2024 11:46:37 GMT+0000 (Coordinated Universal Time)
2 Closed Completed and in use Fri May 24 2024 11:53:20 GMT+0000 (Coordinated Universal Time)
#1 Open
Contract Status
Open
Reason
Recently commenced
Date
Fri May 24 2024 11:46:37 GMT+0000 (Coordinated Universal Time)
#2 Closed
Contract Status
Closed
Reason
Completed and in use
Date
Fri May 24 2024 11:53:20 GMT+0000 (Coordinated Universal Time)

Contract Implementation

Variation to Contract Price:

GH¢ 0.00

Escalation of Contract Price:

GH¢ 0.00

Variation to Contract Scope:

No

Reasons for Price Changes:

No change in price

Reasons for Scope Changes:

N/A

Reasons for Duration Changes:

No change in duration

Tender Management

Initiation


Procuring Entity:

Shama District Assembly

Procuring Entity Contact Details:

0246153277
info@shamadistrict.gov.gh
P. O. Box 37, Shama

Procurement Process:

Competitive (National Competitive Tendering)

Procurement Method:

Open

Bidder(s):
# Bidder(s) Country
1 Ashcab Co. Ltd Ghana
2 I. B Clements Co. Ltd Ghana
3 Powerful Ventures Limited Ghana
#1 Ashcab Co. Ltd
Bidder
Ashcab Co. Ltd
Country
Ghana
#2 I. B Clements Co. Ltd
Bidder
I. B Clements Co. Ltd
Country
Ghana
#3 Powerful Ventures Limited
Bidder
Powerful Ventures Limited
Country
Ghana

Award


Number of Firms Tendering:

4

Cost Estimate:

GH¢ 473,800.00

Contracting


Contract Administrative Entity:

Shama District Assembly

Contract Type:

Lump Sum

Contract Title:

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture

Contract Firm(s):
# Name of Firm Description
1 Powerful Ventures Ltd
#1 Powerful Ventures Ltd
Name of Firm
Powerful Ventures Ltd
Description
Contract Price:

GH¢ 473,800.00

Contract Scope of Work:

Excavation, Hardcore filling, cutting/ clearing, Concrete works, Reinforcement work, Formwork, Block work, Roofing, Woodwork, ironmongery work, metal work, Plumbing

Contract Start Date:

Thu Sep 15 2022

Contract Duration:

From: Thu Sep 15 2022
To: Tue Mar 14 2023
In Days: 180

Consultant:
# Consultant Description of Role
No data found
No data found
Contract Status:
# Contract Status Reason Date
1 Open Recently commenced Fri May 24 2024 13:05:19 GMT+0000 (Coordinated Universal Time)
#1 Open
Contract Status
Open
Reason
Recently commenced
Date
Fri May 24 2024 13:05:19 GMT+0000 (Coordinated Universal Time)

Contract Implementation

Variation to Contract Price:

Escalation of Contract Price:

Variation to Contract Scope:

Reasons for Price Changes:

Reasons for Scope Changes:

Reasons for Duration Changes:

Project Completion

Project Status:
# Project Status Reason Date
1 Completed Completed and in use. Fri May 24 2024 13:46:47 GMT+0000 (Coordinated Universal Time)
#1 Completed
Project Status
Completed
Reason
Completed and in use.
Date
Fri May 24 2024 13:46:47 GMT+0000 (Coordinated Universal Time)
Completion Cost:

GH¢ 473,800.00

Completion Date:

Tue Mar 14 2023

Scope at Completion:

1 no.2 unit KG Block with Office, Kitchen and Urinal/ Toilet Facilities and Furniture

Reasons for Project Changes:
# Reason Recorded Date
No data found
No data found
Reference to Audit and Evaluation Reports:
# Reference to Evaluation Report Recorded Date
No data found
No data found

Milestone

There are no milestones

Project Images

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

Image 1

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

Image 2

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

Image 3

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

Image 4

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

Image 5

Construction Of 1 No.2 Unit Kg Block With Office, Kitchen And Urinal/ Toilet Facilities And Furniture For Anto D/A Primary School

Image 6