Project Identification
The overall objective of the project is to expand infrastructural facilities within Kokompe industrial enclave to create the necessary environment for local economic development.
Construction of 25 No. Garage Units
Construction of Skills and Training Centre
Construction of Flush Toilet and Shower
Power and Water Supply
Economy
Kokompe - Takoradi
Construction of 25 No. Garages and Two-Storey Skills & Training Centre
Ministry Of Local Government And Rural Development/Sekondi-Takoradi Metropolitan Assembly
Construction Of 25 No. Garage Units Construction Of Skills And Training Centre Construction Of Flush Toilet And Shower Power And Water Supply
There Was An Environmental Impact Assessment Which Identified Potential Impacts On The Physical, Biological And Socio-Economic/Cultural Environments, Occupational Safety, Health And Welfare Of The Employees.
N/A
30 years
Agence FrançAise De DéVeloppement
Sekondi-Takoradi Metropolitan Assembly
0312046371
info@stma.gov.gh
STMA Road
International Competitive Tendering (Ict)
Open
# | Bidder(s) | Country |
---|---|---|
No data found |
8
GH¢ 3,500,000.00
Ministry Of Local Government And Rural Development/Sekondi-Takoradi Metropolitan Assembly
Construction
Construction Of 25 No. Garages And Two-Storey Skills & Training Centre
# | Name of Firm | Description |
---|---|---|
1 | M/S Hydronomics Limited | Hydronomics Limited is a privately owned Ghanaian company incorporated in April 2004 and commenced operations in May 2004. Our Ministry of Water and Resources, Works and Housing classification is K1D1. Fields of Expertise: 1. Pipe Water System Construction The Pipe Water System Construction aspect of the company includes; Hydrogeological studies, borehole drilling, borehole rehabilitation, handpump installation, handpump performance monitoring, groundwater salinity mapping, mapping of contaminant plumes, water quality monitoring, supply of groundwater related equipment and training of young professionals in the water sector. 2. Building Constructions Hydronomics engages in the building of apartments, office complexes, residential units, garages, warehouses, church buildings, markets and malls. 3. Road constructions The company has also been involved in the construction of a number of roads cutting across feeder roads to urban roads. We also engage in resealing of gravel roads, building of culverts and bridges. 4. Mining Hydronomics is also engaged in various forms of mining activities such as earthworks and mining construction. |
GH¢ 3,454,989.45
- Construction of 25 No. Garage Units - Construction of Skills and Training Centre - Construction of Flush Toilet and Shower - Power and Water Supply
Mon Jan 05 2015
From:
Mon Jan 05 2015
To:
Fri Feb 10 2017
In Days: 767
# | Consultant | Description of Role |
---|---|---|
1 | Lamda Consult Limited | Consultant on Project |
# | Contract Status | Reason | Date |
---|---|---|---|
1 | Closed | Fully completed, commissioned and in use | Fri Mar 26 2021 16:56:40 GMT+0000 (Coordinated Universal Time) |
GH¢ 0.00
GH¢ 0.00
N/A
Changes in market prices and the contract made provision for such changes
Construction of Chain Link to protect the skills training centre and Ramps to make the facility disability-friendly and also for vehicles to be able to enter the garages for work to be done on it. This was not added directly to the contract but was packaged in addition to some additional works on another project (Integrated Social Centre - Effiakuma)
Duration changes: The was issues with land management and re-organisation of the place for the new facility be constructed
# | Project Status | Reason | Date |
---|---|---|---|
1 | Completion | Fully completed, commissioned and in use | Fri Mar 26 2021 17:03:49 GMT+0000 (Coordinated Universal Time) |
GH¢ 3,454,989.50
Fri Feb 10 2017
Construction of 25 No. Garage Units Construction of Skills and Training Centre Construction of Flush Toilet and Shower Power and Water Supply
# | Reason | Recorded Date |
---|---|---|
1 | There Was Inadequate Understanding Of The Project By The Project Beneficiaries Which Affected The Start Date Of The Project. It Was In The Grapevine That The Assembly Wanted To Take Over Their Land For A Different Project And This Affected The Movement Of Artisans To Pave Way For The Project To Start. The Assembly Had To Engage The Leadership Of The Beneficiaries On Several Occasions Address Their Concerns. This Took Two Months To Resolve Before The Contractor Was Given The Permission To Possess The Sites. The Contract Was Signed In October 2014 But The Contractor Was Able To Take Possession Of Site In January 2015. The Project Beneficiaries. | Wed Jan 06 2016 |
# | Reference to Evaluation Report | Recorded Date |
---|---|---|
No data found |
Fri Jan 15 2010
The overall objective of the project is to expand infrastructural facilities within Kokompe industrial enclave to create the necessary environment for local economic development.
Fri Feb 10 2012
•Selected after extensive consultation with kokompe artisans and trade groups •Financed through the AFD under the Ghana Urban Management Pilot Program •Scope of work (construction of 25 garages, skills training centre with ancillary facilities)
Thu May 15 2014
•May, 2015 - Advertisement for Expression of Interest on Daily Graphic •8 (Number of Firms Tendering) •Sept., 2015 - Approval by Central Tender Review Board •Sept., 2014 - Contract Signing with M/S Hydronomics Ltd •GH¢ 3,454,989.45 (Cost Estimate)
Thu Jan 15 2015
•15/01/2015 (Contract Start Date)•24 months(Contract Duration)•Completed (Contract Status)
Mon Jan 26 2015
• MLRD/STMA (Contract Administering Entity) • GH¢3,454,989.45 (Cost Estimate) • Construction of 25 No. Garages and Two-Storey Skills & Training Centre, Flush toilets (Scope)•M/S Hydronomics Ltd (Contract Firm)
Thu Feb 02 2017
• Construction Of 25 No. Garage Units Construction Of Skills And Training Centre Construction Of Flush Toilet And Shower Power And Water Supply, chain-link and ramps (Scope at Completion)
Thu Feb 02 2017
• Completed (Project Current Status) • GH¢3,437,861.70 (Completion Cost) • 2nd February, 2017 (Completion Date)
Wed Mar 01 2017
• Addition of chain-links and ramps (Variation to Scope) •11 months time overrun (Variation to Contract Duration) •Refusal of some of the trade groups to vacate project site resulted in delays(Reason/s for Change in Contract Duration)
Thu Mar 18 2021
• CoST 2nd Assurance Report (Reference to Audit & Evaluation Report)